Blowout preventer
30/11/2015
A blowout preventer (BOP) is a large, specialized valve or similar mechanical device, used to seal, control and monitoroil and gas wells to prevent blowout, the uncontrolled release of crude oil and/or natural gas from well. They are usually installed redundantly in stacks.
Blowout preventers were developed to cope with extreme erratic pressures and uncontrolled flow (formation kick) emanating from a well reservoir during drilling. Kicks can lead to a potentially catastrophic event known as a blowout. In addition to controlling the downhole (occurring in the drilled hole) pressure and the flow of oil and gas, blowout preventers are intended to prevent tubing (e.g. drill pipe and well casing), tools and drilling fluid from being blown out of the wellbore (also known as bore hole, the hole leading to the reservoir) when a blowout threatens. Blowout preventers are critical to the safety of crew, rig (the equipment system used to drill a wellbore) and environment, and to the monitoring and maintenance of well integrity; thus blowout preventers are intended to provide fail-safety to the systems that include them.
The term BOP (pronounced B-O-P, not "bop") is used in oilfield vernacular to refer to blowout preventers. The abbreviated term preventer, usually prefaced by a type (e.g. ram preventer), is used to refer to a single blowout preventer unit. A blowout preventer may also simply be referred to by its type (e.g. ram).
The terms blowout preventer, blowout preventer stack and blowout preventer system are commonly used interchangeably and in a general manner to describe an assembly of several stacked blowout preventers of varying type and function, as well as auxiliary components. A typical subsea deepwater blowout preventer system includes components such as electrical and hydraulic lines, control pods, hydraulic accumulators, test valve, kill and choke lines and valves, riser joint, hydraulic connectors, and a support frame.
Two categories of blowout preventer are most prevalent: ram and annular. BOP stacks frequently utilize both types, typically with at least one annular BOP stacked above several ram BOPs.
(A related valve, called an inside blowout preventer, internal blowout preventer, or IBOP, is positioned within, and restricts flow up, the drillpipe. This article does not address inside blowout preventer use.)
Blowout preventers are used on land wells, offshore rigs, and subsea wells. Land and subsea BOPs are secured to the top of the wellbore, known as the wellhead. BOPs on offshore rigs are mounted below the rig deck. Subsea BOPs are connected to the offshore rig above by a drilling riser that provides a continuous pathway for the drill string and fluids emanating from the wellbore. In effect, a riser extends the wellbore to the rig.
BOPs come in two basic types, ram and annular. Both are often used together in drilling rig BOP stacks, typically with at least one annular BOP capping a stack of several ram BOPs
Ram blowout preventer[edit]
A Patent Drawing of the Original Ram-type Blowout Preventer, by Cameron Iron Works (1922).
Blowout Preventer diagram showing different types of rams. (a) blind ram (b) pipe ram and (c) shear ram.
The ram BOP was invented by James Smither Abercrombie and Harry S. Cameron in 1922, and was brought to market in 1924 by Cameron Iron Works.[2]
A ram-type BOP is similar in operation to a gate valve, but uses a pair of opposing steel plungers, rams. The rams extend toward the center of the wellbore to restrict flow or retract open in order to permit flow. The inner and top faces of the rams are fitted with packers (elastomeric seals) that press against each other, against the wellbore, and around tubing running through the wellbore. Outlets at the sides of the BOP housing (body) are used for connection to choke and kill lines or valves.
Rams, or ram blocks, are of four common types: pipe, blind, shear, and blind shear.
Pipe rams close around a drill pipe, restricting flow in the annulus (ring-shaped space between concentric objects) between the outside of the drill pipe and the wellbore, but do not obstruct flow within the drill pipe. Variable-bore pipe rams can accommodate tubing in a wider range of outside diameters than standard pipe rams, but typically with some loss of pressure capacity and longevity.
Blind rams (also known as sealing rams), which have no openings for tubing, can close off the well when the well does not contain a drill string or other tubing, and seal it.
Patent Drawing of a Varco Shaffer Ram BOP Stack. A shear ram BOP has cut the drillstring and a pipe ram has hung it off.
Schematic view of closing shear blades
Shear rams cut through the drill string or casing with hardened steel shears.
Blind shear rams (also known as shear seal rams, or sealing shear rams) are intended to seal a wellbore, even when the bore is occupied by a drill string, by cutting through the drill string as the rams close off the well. The upper portion of the severed drill string is freed from the ram, while the lower portion may be crimped and the “fish tail” captured to hang the drill string off the BOP.
In addition to the standard ram functions, variable-bore pipe rams are frequently used as test rams in a modified blowout preventer device known as a stack test valve. Stack test valves are positioned at the bottom of a BOP stack and resist downward pressure (unlike BOPs, which resist upward pressures). By closing the test ram and a BOP ram about the drillstring and pressurizing the annulus, the BOP is pressure-tested for proper function.
The original ram BOPs of the 1920s were simple and rugged manual devices with minimal parts. The BOP housing (body) had a vertical well bore and horizontal ram cavity (ram guide chamber). Opposing rams (plungers) in the ram cavity translated horizontally, actuated by threaded ram shafts (piston rods) in the manner of a screw jack. Torque from turning the ram shafts by wrench or hand wheel was converted to linear motion and the rams, coupled to the inner ends of the ram shafts, opened and closed the well bore. Such screw jack type operation provided enough mechanical advantage for rams to overcome downhole pressures and seal the wellbore annulus.
Hydraulic rams BOPs were in use by the 1940s. Hydraulically actuated blowout preventers had many potential advantages. The pressure could be equalized in the opposing hydraulic cylinders causing the rams to operate in unison. Relatively rapid actuation and remote control were facilitated, and hydraulic rams were well-suited to high pressure wells.
Because BOPs are depended on for safety and reliability, efforts to minimize the complexity of the devices are still employed to ensure longevity. As a result, despite the ever-increasing demands placed on them, state of the art ram BOPs are conceptually the same as the first effective models, and resemble those units in many ways.
Hydril Company's Compact BOP Ram Actuator Assembly Patent Drawing
Ram BOPs for use in deepwater applications universally employ hydraulic actuation. Threaded shafts are often still incorporated into hydraulic ram BOPs as lock rods that hold the ram in position after hydraulic actuation. By using a mechanical ram locking mechanism, constant hydraulic pressure need not be maintained. Lock rods may be coupled to ram shafts or not, depending on manufacturer. Other types of ram locks, such as wedge locks, are also used.
Typical ram actuator assemblies (operator systems) are secured to the BOP housing by removable bonnets. Unbolting the bonnets from the housing allows BOP maintenance and facilitates the substitution of rams. In that way, for example, a pipe ram BOP can be converted to a blind shear ram BOP.
Shear-type ram BOPs require the greatest closing force in order to cut through tubing occupying the wellbore. Boosters (auxiliary hydraulic actuators) are frequently mounted to the outer ends of a BOP’s hydraulic actuators to provide additional shearing force for shear rams.
Ram BOPs are typically designed so that well pressure will help maintain the rams in their closed, sealing position. That is achieved by allowing fluid to pass through a channel in the ram and exert pressure at the ram’s rear and toward the center of the wellbore. Providing a channel in the ram also limits the thrust required to overcome well bore pressure.
Single ram and double ram BOPs are commonly available. The names refer to the quantity of ram cavities (equivalent to the effective quantity of valves) contained in the unit. A double ram BOP is more compact and lighter than a stack of two single ram BOPs while providing the same functionality, and is thus desirable in many applications. Triple ram BOPs are also manufactured, but not as common.
Technological development of ram BOPs has been directed towards deeper and higher pressure wells, greater reliability, reduced maintenance, facilitated replacement of components, facilitated ROV intervention, reduced hydraulic fluid consumption, and improved connectors, packers, seals, locks and rams. In addition, limiting BOP weight and footprint are significant concerns to account for the limitations of existing rigs.
The highest-capacity large-bore ram blowout preventer on the market, as of July 2010, Cameron’s EVO 20K BOP, has a hold-pressure rating of 20,000 psi, ram force in excess of 1,000,000 pounds, and a well bore diameter of 18.75 inches.
Annular blowout preventer
The annular blowout preventer was invented by Granville Sloan Knox in 1946; a U.S. patent for it was awarded in 1952.[3] Often around the rig it is called the "Hydril", after the name of one of the manufacturers of such devices.
An annular-type blowout preventer can close around the drill string, casing or a non-cylindrical object, such as the kelly. Drill pipe including the larger-diameter tool joints (threaded connectors) can be "stripped" (i.e., moved vertically while pressure is contained below) through an annular preventer by careful control of the hydraulic closing pressure. Annular blowout preventers are also effective at maintaining a seal around the drillpipe even as it rotates during drilling. Regulations typically require that an annular preventer be able to completely close a wellbore, but annular preventers are generally not as effective as ram preventers in maintaining a seal on an open hole. Annular BOPs are typically located at the top of a BOP stack, with one or two annular preventers positioned above a series of several ram preventers.
An annular blowout preventer uses the principle of a wedge to shut in the wellbore. It has a donut-like rubber seal, known as an elastomeric packing unit, reinforced with steel ribs. The packing unit is situated in the BOP housing between the head and hydraulic piston. When the piston is actuated, its upward thrust forces the packing unit to constrict, like a sphincter, sealing the annulus or openhole. Annular preventers have only two moving parts, piston and packing unit, making them simple and easy to maintain relative to ram preventers.
The original type of annular blowout preventer uses a “wedge-faced” (conical-faced) piston. As the piston rises, vertical movement of the packing unit is restricted by the head and the sloped face of the piston squeezes the packing unit inward, toward the center of the wellbore.
In 1972, Ado N. Vujasinovic was awarded a patent for a variation on the annular preventer known as a spherical blowout preventer, so-named because of its spherical-faced head.[4] As the piston rises the packing unit is thust upward against the curved head, which constricts the packing unit inward. Both types of annular preventer are in common use
Deepwater Horizon blowout
During the Deepwater Horizon drilling rig explosion incident on April 20, 2010, the blowout preventer should have been activated automatically, cutting the drillstring and sealing the well to preclude a blowout and subsequent oil spill in the Gulf of Mexico, but it failed to fully engage. Underwater robots (ROVs) later were used to manually trigger the blind shear ram preventer, to no avail.
As of May 2010 it was unknown why the blowout preventer failed.[5] Chief surveyor John David Forsyth of the American Bureau of Shipping testified in hearings before the Joint Investigation[6] of the Minerals Management Service and the U.S. Coast Guard investigating the causes of the explosion that his agency last inspected the rig's blowout preventer in 2005.[7] BP representatives suggested that the preventer could have suffered a hydraulic leak.[8] Gamma-ray imaging of the preventer conducted on May 12 and May 13, 2010 showed that the preventer's internal valves were partially closed and were restricting the flow of oil. Whether the valves closed automatically during the explosion or were shut manually by remotely operated vehicle work is unknown.[8] A statement released by Congressman Bart Stupak revealed that, among other issues, the emergency disconnect system (EDS) did not function as intended and may have malfunctioned due to the explosion on the Deepwater Horizon.[9]
The permit for the Macondo Prospect by the Minerals Management Service in 2009 did not require redundant acoustic control means.[10] Inasmuch as the BOPs could not be closed successfully by underwater manipulation (ROV Intervention), pending results of a complete investigation, it is uncertain whether this omission was a factor in the blowout.
Documents discussed during congressional hearings June 17, 2010, suggested that a battery in the device's control pod was flat and that the rig's owner, Transocean, may have "modified" Cameron's equipment for the Macondo site (including incorrectly routing hydraulic pressure to a stack test valve instead of a pipe ram BOP) which increased the risk of BOP failure, in spite of warnings from their contractor to that effect. Another hypothesis was that a junction in the drilling pipe may have been positioned in the BOP stack in such way that its shear rams had an insurmountable thickness of material to cut through.[11]
It was later discovered that a second piece of tubing got into the BOP stack at some point during the Macondo incident, potentially explaining the failure of the BOP shearing mechanism.[12] As of July 2010 it was unknown whether the tubing might have been casing that shot up through the well or perhaps broken drill pipe that dropped into the well. The DNV final report indicated that the second tube was the segment of the drill string that was ejected after being cut by the blow out preventer shears.
On July 10, 2010 BP began operations to install a sealing cap, also known as a capping stack, atop the failed blowout preventer stack. Based on BP's video feeds of the operation the sealing cap assembly, called Top Hat 10, included a stack of three blind shear ram BOPs manufactured by Hydril (a GE Oil & Gas company), one of Cameron's chief competitors. By July 15 the 3 ram capping stack had sealed the Macondo well, if only temporarily, for the first time in 87 days.
The U.S. government wanted the failed blowout preventer to be replaced in case of any pressure change that occurs when the relief well intersected with the well.[13] On September 3 at 1:20 p.m. CDT the 300 ton failed blowout preventer was removed from the well and began being slowly lifted to the surface.[13] Later that day a replacement blowout preventer was placed on the well.[14] On September 4 at 6:54 p.m. CDT the failed blowout preventer reached the surface of the water and at 9:16 p.m. CDT it was placed in a special container on board the vessel Helix Q4000.[14] The failed blowout preventer was taken to a NASA facility in Louisiana for examination[14] by Det Norske Veritas (DNV).
On 20 March 2011, DNV presented their report to the US Department of Energy.[15] Their primary conclusion was that while the rams succeeded in partly shearing through the drill pipe they failed to seal the bore because the drill pipe had buckled out of the intended line of action of the rams (because the drill string was caught at a tool joint in the upper annular BOP valve), jamming the shears and leaving the drill string shear actuator unable to deliver enough force to complete its stroke and fold the cut pipe over and seal the well. They did not suggest any failure of actuation as would be caused by faulty batteries. The upper section of the blow out preventer failed to separate as designed due to numerous oil leaks compromising hydraulic actuator operation, and this had to be cut free during recovery.